We had a great day again today. After getting the footers all dug,prepped with rebar including tying 4  8‘ rebar columns yesterday, today we moved along. We poured the footers first thing and then began laying block.
We finished the day with the walls up close to 4‘.
   -  Attached are pictures as follows (not in order, sorry):



 -The barrio teams heading out.

-Joe and Tim at the construction site
-George and Jacob sifting our sand used for mortar (lots of pebbles and small stones)
-Progress picture - the tall wall separates the school from the street. There will be 2 windows in the wall that will be used for the local people to get the filtered water.